March | |
---|---|
until mid March 2021 | Finalizing the "Quick start Guides" for each sensor type. |
15. March 2021 | Deadline for non-EU shipments: the packing lists must be sent to Tobias: tost@norceresearch.no |
April | |
12. - 14. April 2021 | Test run at the facility: tank insulation, pump test,... |
30. April 2021 | Deadline for EU shipments: The packing lists must be sent to Tobias: tost@norceresearch.no |
June | |
07. June 2021 | Deadline for instruments arriving at GEOMAR (non-EU shipments) |
15. June 2021 | Deadline for instruments arriving at VLIZ (EU shipments) |
16. - 25. June 2021 | Setting up the infrastructure at the Marine station Ostend by the core team |
25. - 27. June 2021 | Test run with all instruments running |
28. June - 09. July 2021 | Inter-comparison |
July | |
10./11. July 2021 | Dismantle instruments, pack |
August | |
02. August 2021 | Instruments will be shipped back to participants. If this date is too late, please let Tobias know and we arrange differently. |
August onwards | Preparing and publishing results. |
Fall 2021 | |
October/November 2021 | 2-3 day (virtual) meeting to discuss the results and science around it. |